You are about to pay a token for an under-construction flat in Pune. The brochure says possession in 2028. How much should you trust that date?
You do not have to guess. Every project in Maharashtra files its completion date with MahaRERA, and every change to that date stays on the public record. We read those records for eight Pune areas: Kharadi, Upper Kharadi, Wagholi, Lohegaon, Keshav Nagar, Hinjawadi, Wakad and Baner. Here is what they show, and how to check any project yourself before you pay.
The short answer: about 1 in 5 projects moved their date
As of 18 November 2026, 49 of the 243 home projects still being built in these eight areas (20%) have had their completion date moved 3 months or more later by the builder since registration.
That count leaves out the 4 months MahaRERA itself added to most projects in August 2026 (Order 66/2026). That extension applied to almost everyone, so it says nothing about a particular builder. The 49 are moves the builders made on their own.
When a date moves, it rarely moves a little. In Wagholi, Kharadi and Lohegaon, where most of these projects are, the usual move is 2 to 3 years.
Area by area
| Area | Projects being built | Moved 3+ months by the builder | Usual move |
|---|---|---|---|
| Wagholi | 94 | 25 (27%) | 32 months |
| Kharadi | 50 | 11 (22%) | 24 months |
| Lohegaon | 60 | 9 (15%) | 36 months |
| Upper Kharadi | 21 | 1 (5%) | 3 months |
| Keshav Nagar | 6 | 0 | – |
| Wakad | 5 | 1 (20%) | 8 months |
| Hinjawadi | 4 | 0 | – |
| Baner | 3 | 2 (67%) | 12 months |
| All eight areas | 243 | 49 (20%) |
"Usual move" is the middle move among the projects whose date moved. A project registered tower by tower is counted once. Hinjawadi, Wakad and Baner have only a handful of projects in this count, so read their percentages with care.
What stands out:
- Wagholi has the most projects and the highest share of moved dates. More than 1 in 4 projects there have moved, usually by more than two and a half years.
- Kharadi is close behind at more than 1 in 5, usually by two years.
- Upper Kharadi has kept its dates best so far: 1 of 21, and that one by 3 months. A good record so far is not a promise, so check each project again as its date gets closer.
The biggest single moves are older projects: one Kharadi project was filed for March 2019 at registration and now shows July 2028, nine years later.
What a moved date means for you
A moved date is not always a bad sign. Approvals, a change in plan or a phase being split can all move a date. But it changes your numbers:
- Rent and EMI together for longer. If you pay rent and start an EMI on a construction-linked plan, every extra month costs you both.
- Pre-EMI interest. If the bank releases money as construction goes on, you pay interest on that part from day one.
- Your plans. A school year, a job move or a wedding planned around the brochure date.
So the question is not only "is it on time?" but "how much did this builder move dates before, and why?"
How to check a project yourself in 5 minutes
- Find the MahaRERA number. It must be printed on every ad and brochure. No number, no booking.
- Open the project on MahaRERA (maharera.maharashtra.gov.in) and compare two dates: the completion date filed at registration and the date filed now. If they differ, look at the extension history and its reasons.
- Subtract MahaRERA's own extension. If the only change is the 4 months from August 2026, the builder has not moved the date.
- Look at homes booked. MahaRERA shows how many homes are booked out of the total. A project selling steadily has cash coming in to build.
- Check the builder's other projects. Did their earlier projects in Pune finish near the filed date? One delayed project can be bad luck; a pattern is not.
If you would rather not dig through MahaRERA's pages, you can type a project's name or MahaRERA number into this free Pune project check. It shows the first and current filed dates, how much the date moved, and homes booked, all from MahaRERA.
Five questions to ask before you pay a token
- "What is the completion date filed with MahaRERA today, and has it ever changed?" Compare the answer with the record, not the brochure.
- "If the date moved, why?" An approval delay is different from slow construction.
- "Which tower or phase am I buying in, and what is its own date?" Big projects register phases separately, and each has its own date.
- "Is the payment plan linked to construction stages?" Then you pay as the building rises, not ahead of it.
- "What does the agreement say about delay?" Under the RERA Act (Section 18), if possession is late you can ask for interest for every month of delay, or withdraw and get your money back with interest. Read that clause before you sign.
One more rule worth knowing: under RERA (Section 13), a builder cannot take more than 10% of the price before a registered agreement for sale.
If the date has already passed
If a project's filed completion date is behind it and you are offered a "ready" flat, ask for the occupancy certificate (OC). Without an OC, the building is not legally ready to live in, whatever the site looks like.
Where these numbers come from
Every project MahaRERA lists in these eight Pune areas, read from its public project pages and read again when MahaRERA marks a change. Nothing is estimated: a figure MahaRERA did not publish is left out.
Source: Avasetu Pune MahaRERA tracker, from MahaRERA public records, as of 18 November 2026. The full area table, the biggest moves and each project's date history are on that page.
Written by the Avasetu team, Pune.